Temporary Closure of Stony Run Path
Caroline Wayner, President of Wyndhurst Improvement Association, has forwarded along this important information from the Baltimore Department of Public Works (DPW) to the Roland Park Civic League.
While inspecting sewer lines in Tuxedo Park near the Stony Run path, DPW has found an old terra cotta pipe in danger of imminent collapse. Were it to collapse, it would severely impact the sewer system of the surrounding neighborhood. DPW is going to fix this right away, but the procedure will require the closure Stony Run path between Gladstone and Deepdene for up to two weeks. Please see the following map:
The pipe in question runs from the dead-end of Colorado Avenue and under the Stony Run.
Tree removal will begin this week. The Friends of Stony Run, Blue Water Baltimore, the North Stony Run Green Team, and the City’s Urban Forestry Division are working with neighborhood groups to make sure that plenty of native trees, shrubs and other plants will replace what is removed. As it happens, much of what is being removed is invasive and undesirable.
Excavation of the dirt above the pipe, which lies 10 feet under, will begin after tree removal. Then the repairs will be made and the path rebuilt. Replanting will commence after September 15.
DPW has advised the Wyndhurst Improvement Association that all work should be finished by the start of public school, which is Monday, August 29th.